Dec 1, 2025
Routine
17C - physical facilities installed, maintained, and clean
Regulation: 511-6-1.07(2)(a) - floor, walls, & ceilings, cleanability (c)
Observed open ceiling in the kitchen and bad ceiling in the bar area. I advised the PIC to replace the missing ceiling in the kitchen and the bad ceiling above the bar area. 511-6-1.07(2)(a) - Floor, Walls, & Ceilings, Cleanability (C) (2) Design, Construction, and Installation.
(a) Floors, Walls, and Ceilings, Cleanability. Except as specified under subsection (2)(d) of this Rule and except for antislip floor coverings or applications that may be used for safety reasons, floors, floor coverings, walls, wall coverings, and ceilings shall be designed, constructed, and installed so they are smooth and easily cleanable.