Mar 12, 2026
Re-inspection
6904 LAUREL ISLAND PKWY KINGSLAND, GA 31548
Inspection scores over time for this facility.
Georgia inspection history is score-based, with violations grouped under each recorded inspection.
Re-inspection
Permit/Opening
Regulation: 511-3-5-.23(5)(a) - (a) during operation, disinfectant levels are less than the minimum level specified in dph rule 511-3-5-.17. if the level of the disinfectant used is not specified in dph rule 511-3-5-.17, the disinfectant must be approved and kept at levels determin
At time of inspection, the free chlorine level registered at 1.54 ppm (free chlorine must be at least 2.00 ppm). CPO states he will increase the output of the salt cell and of the chlorinator. The pool must remain closed, until the free chlorine level is within range (2.00 - 10.00 ppm) AND the pool has passed re-inspection.
Regulation: 511-3-5-.17(4) - (4) stabilizer (if used) cyanuric acid,ppm ideal: 30-50 maximum: 90 comments: if stabilizer is: too high: - may reduce chlorine efficacy too low: - chlorine residual rapidly destroyed by sunlight note: stabilizer is not needed in indoor or br
At time of inspection, the cyanuric acid (CYA) registered at 130 ppm (CYA must be 90 ppm or less). CPO states he will drain some water and add some fresh water, until CYA is under 90 ppm.
Routine
Permit/Opening
Routine
Regulation: 511-3-5-.17(1) - (1) disinfectant levels (a) free chlorine, ppm in pools not using cyanuric acid or a stabilized chlorine compound use (b),1.-5.
At time of inspection, the combined chlorine registered at 0.57 ppm (combined chlorine must be 0.4 ppm or less). CPO will superchlorinate the pool to burn off the combined chlorine and some of the excess stabilizer.
Regulation: 511-3-5-.06(1)(l) - (l) open joints or gaps larger than three-sixteenths inch wide or with vertical elevations exceeding 1/4 inches shall be rectified using appropriate fillers. construction joints where pool coping meets the decks shall be watertight and shall not allo
At time of inspection, there is a considerable gap between the rows of pavers at the shallow end of the pool. CPO will evaluate and have the gap filled/sealed.
Permit/Opening
Regulation: 511-3-5-.06(3)(f)1. - 1. handrails, if removable, shall be installed in such a way that they cannot be removed without the use of tools.
At time of inspection, one of the handrails was loose. The maintenance supervisor made note and will tighten the handrail.
Re-inspection
Permit/Opening
Regulation: 511-3-5-.18(10)(c ) - (c) an operable, hard-wired, conventional telephone line or continuous powered source, weatherproof emergency phone shall be permanently installed in a conspicuous location within the pool enclosure and must be readily available to bathers at all tim
Emergency phone is not operational, at time of inspection. CA: PIC has contacted Hargray to check into the issue. PIC will call EH office to schedule re-inspection.