Regulation: 511-3-5-.07(1)(a) - (a) the equipment for a swimming pool shall be of adequate size to turn over the entire pool water capacity. the turnover rate for pools constructed after the adoption of this chapter shall not exceed the sum of one and one-half times the average wat
Observed turnover rate of 160 GPM. Turnover rate for this pool must be 245 GPM or higher.
Observed skimmers missing weirs. All skimmers must have a weir.
Regulation: 511-3-5-.06(3)(f)1. - 1. handrails, if removable, shall be installed in such a way that they cannot be removed without the use of tools.
Observed several hand rails loose. Must fix.
Permit/Opening
Regulation: 511-3-5-.07(4)(a) - (a) a pressure or vacuum gauge or other means of indicating system condition shall be provided in the circulation system in an easily readable location.
Must install effluent pressure gauge.
Routine
Regulation: 511-3-5-.07(1)(b) - (b) turnover rates for pools by type listed below: type
Observed a turnover rate of 0 GPM. The required turnover rate for this pool is 245 GPM.
Regulation: 511-3-5-.11(3)(d) - (d) each skimmer shall have a weir that adjusts automatically to variations in water level over a minimum range of four inches.
Observed several skimmers missing weirs. All skimmers must have a weir.
Permit/Opening
Routine
Regulation: 511-3-5-.07(1)(b) - (b) turnover rates for pools by type listed below: type
Flow meter is reading around 180 GPM. The turnover rate for this pool is 245 GPM.