Permit/Opening
1319 KING AVE KINGSLAND, GA 31548
Inspection scores over time for this facility.
Georgia inspection history is score-based, with violations grouped under each recorded inspection.
Permit/Opening
Routine
Regulation: 511-3-5-.07(4)(b) - (b) a flow meter measuring the rate of flow through the filter system with an appropriate range readable in gallons per minute (gpm) and accurate within ten percent actual flow shall be provided. the flow indicator shall be capable of measuring from
At time of inspection, the flow meter appears to be stuck. Repair/replace the flow meter.
Regulation: 511-3-5-.10(1)(c )1.ii. - (ii) the fitting shall not constitute a hazard to the user.
At time of inspection, the return inlet covers are missing from the spa. Replace return inlet covers.
Re-inspection
Regulation: 511-3-5-.07(4)(b) - (b) a flow meter measuring the rate of flow through the filter system with an appropriate range readable in gallons per minute (gpm) and accurate within ten percent actual flow shall be provided. the flow indicator shall be capable of measuring from
At time of follow-up inspection, the flow meter is still not functioning. CPO will repair/replace the flow meter.
Permit/Opening
Regulation: .17((1)(c) - proper disinfectant level
At time of inspection, free chlorine (FCL) level registered at 10.55 ppm (FCL for spas must be within 3.00 - 10.00 ppm). CPO is adding more water, as the water level was a little low when he arrived.
Regulation: 511-3-5-.23(5)(b) - (b) during operation, the ph is less than the minimum or more than the maximum levels allowed in dph rule 511-3-5-.l7.
At time of inspection, the pH registered at 8.3 (pH must be within 7.2 - 7.8). CPO added muriatic acid to the spa, to lower the pH to within acceptable range.
Regulation: 511-3-5-.07(4)(b) - (b) a flow meter measuring the rate of flow through the filter system with an appropriate range readable in gallons per minute (gpm) and accurate within ten percent actual flow shall be provided. the flow indicator shall be capable of measuring from
At time of inspection, the flow meter is not functioning. Repair/replace flow meter.
Regulation: 511-3-5-.07(4)(a) - (a) a pressure or vacuum gauge or other means of indicating system condition shall be provided in the circulation system in an easily readable location.
At time of inspection, the pressure gauge on the filter is broken. Replace pressure gauge.
At time of inspection, the total alkalinity registered at 245 ppm (alkalinity must be within 60 - 180 ppm). CPO added muriatic acid to the spa, to lower the pH and the total alkalinity.
Re-inspection
At time of inspection, the pH is still high (8.2, at time of inspection; pH must be 7.2-7.8). PIC will have the CPO adjust. Pool/spa area already closed with door locked (and with "closed" signage), at time of inspection. Spa must remain closed, until pH is within range and spa passes re-inspection.
Regulation: 511-3-5-.07(4)(a) - (a) a pressure or vacuum gauge or other means of indicating system condition shall be provided in the circulation system in an easily readable location.
At time of inspection, the pressure gauge is still not functioning. The facility is still working towards replacing the pressure gauge.
Permit/Opening
Regulation: 511-3-5-.23(5)(a) - (a) during operation, disinfectant levels are less than the minimum level specified in dph rule 511-3-5-.17. if the level of the disinfectant used is not specified in dph rule 511-3-5-.17, the disinfectant must be approved and kept at levels determin
At time of inspection, the disinfectant level is below the minimum level required (spa disinfectant level must be at least 3.00 ppm). CPO will adjust. Pool/spa area already closed with door locked (and with "closed" signage), at time of inspection. Spa must remain closed, until chlorine level is within range and spa passes re-inspection.
Regulation: 511-3-5-.23(5)(b) - (b) during operation, the ph is less than the minimum or more than the maximum levels allowed in dph rule 511-3-5-.l7.
At time of inspection, the pH is 8.1 (pH must be 7.2-7.8). CPO will adjust. Pool/spa area already closed with door locked (and with "closed" signage), at time of inspection. Spa must remain closed, until pH is within range and spa passes re-inspection.
Regulation: 511-3-5-.07(4)(a) - (a) a pressure or vacuum gauge or other means of indicating system condition shall be provided in the circulation system in an easily readable location.
At time of inspection, the pressure gauge is not functioning. Facility will replace the gauge.