13-189(c)(1)- Free-chlorine residuals shall be maintained at 3-10 ppm at all times. Observed FCL of 1.71.
13-202(d): Pool shall have a coast guard approved life saving ring firmly attached to a 1/4"-3/8" diameter throwing rope as long as 1 1/2 times max pool width, or 50ft- whichever is longer. Observed rope handles broken and throwing rope inadequate.
13-187(c): A copy of CPO license shall be conspicuously displayed. Observed CPO license kept in binder in office.
13-187(c): Permit shall be conspicuously displayed. Observed no permit displayed.
13-191(a): All valves and piping in equipment room shall be clearly labeled and water flow direction shall be indicated. Observed labels faded and some pipes without labels.
13-201(k): An adequate supply of toilet paper will be provided at all times. Observed womens restroom without toilet paper.
13-201(b): A deck shower shall be provided and functional. Observed deck shower not functional.
13-201(k) - An adequate supply of liquid soap shall be provided at all times in dressing shower. Observed no liquid soap provided in showers.
13-187(c) - Current inspection report shall be conspicuously posted. Observed no inspection report posted.
13-202(I) - Pool shall have a departmentally approved emergency action plan. Observed incomplete EAP.
13-202(k): Pool shall be supplied with a readily available first aid kit kept stocked and ready for use. Observed first aid kit in need of replacement.
Permit/Opening
Flow meter reading at 180 instead of adequate rate of 208
Routine
Routine
13-190(A) - EQUIPMENT SHALL BE OPERATED TO OBTAIN THE MINIMUM REQUIRED TURNOVER RATE. A POOL WITH SPECIAL FEATURES SHOULD HAVE A 4 HOUR TURNOVER RATE. THIS IS 208 GPM FOR A 50,000 GALLON POOL, OBSERVED FLOW METER READING AT 170.
13-201(K) - SUPPLY OF LIQUID SOAP IN APPROPRIATE DISPENSERS SHALL BE PROVIDED AND BE ACCESSIBLE TO BATHERS. OBSERVED NO LIQUID SOAP IN MALE RESTROOM.
Permit/Opening
Routine
13-189(C)(4) - POOL DISINFECTANT AND PH SHALL BE TESTED AT LEAST TWICE DAILY. POOL WAS ONLY BEING TESTED ONCE DAILY
13-201(k) - at all times, a supply of liquid soap in appropriate dispensers shall be provided to bathers. (No bar soap). Observed no liquid soap provided in showers.
13-187(c) - current most recent inspection report shall be displayed and easily readable by the public at all times. Observed last inspection report not displayed.
13-202(I) - each pool facility shall have in place a departmentally approved emergency action plan (EAP). A written copy shall be located to allow for immediate access in case of an emergency. Observed no emergency action plan available. Provided template.
Routine
13-190(A) - EQUIPMENT SHALL BE OPERATED TO OBTAIN THE MINIMUM REQUIRED TURNOVER RATE. A POOL WITH SPECIAL FEATURES SHOULD HAVE A 4 HOUR TURNOVER RATE. THIS IS 208 GPM FOR A 50,000 GALLON POOL
13-189(C)(4) - POOL DISINFECTANT AND PH SHALL BE TESTED AT LEAST TWICE DAILY. POOL WAS ONLY BEING TESTED ONCE DAILY
13-201(K) - SUPPLY OF LIQUID SOAP IN APPROPRIATE DISPENSERS SHALL BE PROVIDED AND BE ACCESSIBLE TO BATHERS
13-202(I) - EMERGENCY ACTION PLAN MUST BE COMPLETE WITH ALL REQUIRED SECTIONS. EAP MISSING "DRILL PROCEDURES" AND "FECAL ACCIDENTS" SECTIONS